Chancellor's Cabinet Report 06-23-26

Prior Week’s Key Accomplishments:

 

City College:

  1. Harry West Gym AC: A 90% Construction Documents (CD) review with the architects was held on Jun. 15.
  1. Saville Theatre Replacement: A meeting to update President Shabazz and campus leadership was held on Jun. 15, followed by the Division of the State Architect (DSA) pre-application meeting on Jun. 16, focusing on accessibility.
  1. Future Outdoor Amphitheatre: A programming kick-off meeting was held on Jun. 18.

 

Mesa College:

  1. Design Center Improvements: Plans remain under review by the DSA.
  1. Athletics Complex: A Schematic Design (SD) meeting focused on aquatics was held on Jun. 15.
  1. Performing Arts Center / Administration & Parking Structure: SD workshops were held on Jun. 17 and Jun. 18 with a focus on site/landscape/exterior, admin, massing, materiality/finishes, venues, and dance.
  1. Fire Sprinkler Backflow Valve Replacement at Humanities and Multi-Cultural Studies (G-100) Building and Learning Resource Center (LRC) Library: Construction began on Jun. 19.

 

Miramar College:

  1. Performing Arts Center & English/Gallery Project: The Design-Build Entity (DBE) met with campus leadership during the week of Jun. 15 to discuss updated exterior design concepts for the building.
  1. Early Education Center: The district reviewed the increment 1 100% Design Development (DD) deliverable during the week of Jun. 15. The DBE submitted increment 2 of the 50% DD deliverable on Jun. 15.
  1. Police Academy (A2) Building 10 Classrooms Tenant Improvement: Contractor mobilized on Jun. 22.

 

College of Continuing Education:

  1. New College of Continuing Education (CCE) Site: A design kick-off meeting with the stakeholders was held on Jun. 17.
  1. West City Expansion: An SD meeting with stakeholders was held on Jun. 17.
  1. CE-Wide Lighting Inverters: A mandatory pre-bid job walk conference was held on Jun. 18.

 

 Other District Locations:

No items to report.  

 

Coming Week Look-Ahead:

 

City College:

  1. Saville Theatre Replacement: A Design Development (DD) pull planning meeting is scheduled for Jun. 23. Pull planning is a collaborative scheduling method in which project teams work backward from a milestone or completion date to identify the activities, handoffs, and resources needed to keep work flowing efficiently.

 

Mesa College:

  1. Athletics Complex: A revised proposal for additional SD phase and preconstruction services associated with the expanded project scope is under review.
  1. Performing Arts Center / Administration & Parking Structure: The DBE will continue development of the 100% SD deliverable for the PAC building, which is due in mid-July. A DSA pre-application meeting for Phase 1 is scheduled for Jun. 22, followed by a Phase 2 pre-application meeting on Jun. 29.
  1. Design Center Improvements: The 100% Construction Documents (CD) estimate will be reviewed during the week of Jun. 22.
  1. Parking Garage Overhead Door & Gate Replacement (PS) Building: A mandatory pre-bid job walk conference is scheduled for Jun. 26.

 

Miramar College:

  1. Montgomery Field Aviation Instructional Center: The DBE will meet with stakeholders during the week of Jun. 22 to discuss the project’s audiovisual needs.
  1. Performing Arts Center & English/Gallery Building: The DBE will meet with campus leadership during the week of Jun. 22 to discuss the updated exterior design concepts of the building.
  1. Early Education Center: The district will review the increment 2 50% DD deliverable during the week of Jun. 22.
  1. Parking Garage Overhead Door Replacement: A mandatory pre-bid job walk conference is scheduled for Jun. 26.

 

College of Continuing Education:

  1. New College of Continuing Education (CCE) Site: A Request for Proposal (RFP) information session for prospective DBEs is scheduled for Jun. 22. Focus group meetings are scheduled as follows: student support focus group meeting Jun. 22; culinary arts Jun. 23; emeritus/Disability Support Programs and Services (DSPS) Jun. 23; business information technology Jun. 23.
  1. CE Harbor View Parking Garage Overhead Door Replacement: A mandatory pre-bid job walk conference is scheduled for Jun. 26.

 

Other District Locations:

No items to report.  

 

Key Items of Interest:

  1. Operations, Enterprise Services and Facilities (OESF): Preparations for the fiscal year transition continue. Vendor communications have been issued encouraging timely submission of June invoices to support a smooth fiscal year closeout and transition process.
  1. Campus Lighting Luminosity Study Project: Preliminary report received on Jun. 22.
  1. SDCCD/SDSU Joint Science Building at SDSU Mission Valley: A pre-submittal information session for the pending RFQ/P was held on Jun. 18 at San Diego City College.

 

Upcoming Needed Campus Action Items (Time Sensitive):

Miramar College:

  1. Performing Arts Center & English/Gallery Project: Campus feedback on the exterior rendering is being addressed. As a result, the SD deliverable, originally anticipated for Jun. 1, is now expected on Jun. 29. Additional delays in providing feedback may further impact the project schedule.
  1. Montgomery Field Aviation Instructional Center: The district has advised that it may pursue an alternate site location due to approval and regulatory hurdles at Montgomery Field. Design is continuing while other locations are being considered. The DBE recommends pausing design if a location has not been determined by the end of the 100% DD phase. If feedback or direction is not provided soon, design will have to be pushed out even further.