Prior Week’s Key Accomplishments:
City College:
- Hardscape Improvements: Precision Concrete (contractor) addressed resurfacing and grinding work identified during the punch walk on Sept. 25.
Mesa College:
- Hardscape Improvements: Concrete removal was completed in identified areas, on Sep. 22.
- Performing Arts Center / Administration & Parking Structure: A Design Development (DD) workshop with the Venue and Lobbies group was held on Sep. 22. Student engagement events were held during Club Rush, a campuswide event where student organizations, clubs and athletic teams showcase their activities and connect with students, on Sep. 23 and 24. The 100% Schematic Design (SD) estimate review meeting with the Design-Build Entity (DBE) was held on Sep. 24. The 50% DD page-turn review with the DBE was held on Sep. 25.
- Athletics Complex: Student engagement events were held during Club Rush, on Sep. 23 and 24. An SD cost estimate reconciliation between the DBE and district is ongoing. A site logistics and phasing review with campus leadership was held on Sep. 24.
- Design Center Improvements: Addenda 3 and Addenda 4 were issued on Sep. 25, providing contractors with additional information on project management requirements and responses to questions about the bid documents.
Miramar College:
- Early Education Center: The DBE met with campus facilities during the week of Sept. 21 to discuss finishes.
- Aviation Instructional Center: The district reviewed the 50% Construction Document (CD) deliverable during the week of Sep. 21. The DBE hosted a DD page-turn meeting with campus stakeholders on Sep. 22 and developed the “Coming Soon” project sign.
- Pool Deck Resurfacing: A preliminary cost estimate, known as a Rough Order of Magnitude (ROM) estimate, was requested on Sep. 22.
- Performing Arts Center & English/Gallery Building: The DBE hosted a DD meeting on Sep. 24 focused on the canyon, a central section of the building, and the performance venues.
College of Continuing Education:
- Lighting Inverter (Multiple Buildings Across CCE Campuses): Bids were received on Sep. 21.
- New Site for SDCCE: Campus Security and Parking and Business Information Technology (BIT) focus group meetings were held on Sep. 23.
- Educational Cultural Complex (ECC) New Facilities Building: A meeting with stakeholders was held on Sep. 24.
Other District Locations:
No items to report.
Coming Week Look-Ahead:
City College:
- Early Education Center (EEC) Shade Structure: A Division of the State Architect (DSA) submittal is scheduled for Oct. 1.
Mesa College:
- Design Center Improvements: An additional Request for Information (RFI) response addendum, if necessary, will be issued during the week of Sep. 28.
- Athletics Complex: A 50% DD page-turn review meeting is scheduled for Sep. 28. Separate focus group meetings with Aquatics and Gym Striping are also scheduled for Sep. 28.
- Performing Arts Center / Administration & Parking Structure: Focus meetings with Dance, Main Theatre, Drama, and Music are scheduled for Sep. 30.
Miramar College:
- Early Education Center: The DBE will conduct a page-turn review of the 50% CD deliverable with campus and district facilities during the week of Sep. 28.
- Performing Arts Center & English/Gallery Building: The district will review the 50% DD deliverable during the week of Sep. 28.
- Lighting Inverters Replacement at buildings Gym (J), Aquatic Center (P-1), Student Resource Center (K-2), Parking Garage (G-3 & G4), Arts & Humanities (H), Administration (N), Science (S-6), and Advanced Transportation (C-2): Bids are due Sep. 30.
- Aquatic Center Solar Panel System Upgrade: A site scope planning meeting is scheduled for Oct. 1.
- Aviation Instructional Center: The DBE will continue developing the 50% CD deliverable and finalize the new service requirements with SDG&E.
College of Continuing Education:
- New Site for SDCCE: A Student Support focus group meeting is scheduled for Sep. 29.
- West City Expansion: A stakeholder DD meeting is scheduled for Sep. 30.
Other District Locations:
No items to report.
Key Items of Interest
- Simplifier: New system enhancements were released to streamline user management, financial tracking and data entry, along with improvements to reporting capabilities that make information easier to manage and review.
Miramar College
- Microgrid Feasibility Study & Linear Generator: The electrical load recorder was adjusted on Sep. 25 as part of the seven-day recorder relocation.
Upcoming Needed Campus Action Items (Time Sensitive)
No items to report.