Chancellor's Cabinet Report 11-10-26
Bond Measure HH Program Updates
Date: November 10, 2026
To: Chancellor’s Cabinet
From: Dr. Joel L. A. Peterson, Vice Chancellor & Executive Operations Officer
Subject: Bond Program Updates (November 2026)
Prior Week’s Key Accomplishments:
City College:
- Lighting Inverter Replacement (Multiple Buildings): The Notice to Proceed (NTP) was issued to Baker Electric, with an official project start date of Nov. 2.
- Saville Theatre: Fault line investigation and trenching, to assess potential seismic conditions in the landscaped area west of the Learning Resource Center (LRC) building, began on Nov. 2.
- “A” Building Expansion: A site visit to verify the location and condition of the existing telecommunications vault, which houses underground communication cables and connections, was held on Nov. 2. Plans to relocate the existing generator at the Bloom Energy yard, which houses on-site power-generation equipment, were submitted to the Division of the State Architect (DSA) and the City of San Diego on Nov. 6. Plans for the temporary campus bookstore swing space in the Math & Social Science (MS) Building were also submitted to DSA on Nov. 6.
Mesa College:
- Parking Garage Overhead Door Replacement: The Notice to Proceed (NTP) was issued to Eroom, Inc., with an official project start date of Nov. 2.
- Athletics Complex: A security coordination meeting with district police and the Design-Build Entity (DBE) was held on Nov. 3.
- English/Student Support Building: Initial programming focus group meetings with 13 stakeholder groups were held on Nov. 5 and 6, marking the start of the project's programming study.
- Performing Arts Center / Administration & Parking Structure: Design-assist partner evaluations with Mechanical, Electrical and Plumbing (MEP) teams continued during the week of Nov. 2. A review of the 50% Design Development (DD) cost estimate with Kitchell Estimating was also held that week.
Miramar College:
- Pool Deck Replacement and Replaster: The second and final pre-bid job walk conference was held on Nov. 2. Contractor requests for information (RFIs) were due Nov. 4.
- Performing Arts Center & English/Gallery Building: The district continued its review of the 100% DD during the week on Nov. 2.
- Early Education Center: The DBE finalized the pre-construction schedule during the week of Nov. 2.
- Aviation Instructional Center: The district and architect agreed on a proposal to study the potential alternative site and began coordinating execution of the contract amendment.
College of Continuing Education:
- Parking Garage Overhead Door Replacement: The Notice to Proceed (NTP) was issued to Eroom, Inc., with an official project start date of Nov. 2.
- West City Expansion: The 50% DD package was submitted on Nov. 2.
- Educational Cultural Complex (ECC) Ceramics Renovation: A low-voltage telecommunications site walk was held on Nov. 4.
- ECC New Facilities Building: An electrical site walk was held on Nov. 4 to review existing site conditions and coordinate electrical requirements for the project.
- ECC Theatre Renovation: A quarterly community meeting and site walk were held on Nov. 6.
Other District Locations:
No items to report.
Coming Week Look-Ahead:
City College:
- “A” Building Expansion: A right-of-way (ROW) permit application for the Bloom Energy yard relocation is scheduled for submission to the City of San Diego on Nov. 10.
- Business and Technology (BT) Building: Restroom construction is scheduled to begin Nov. 11.
- Saville Theatre: Fault line investigation and trenching in the landscaped area west of the LRC building will continue through Nov. 13.
Mesa College:
- Design Center Improvements: A follow-up move and logistics coordination meeting is scheduled for Nov. 11.
- English/Student Support Building: A programming check-in meeting with the DBE is scheduled for Nov. 11.
- Athletics Complex: A meeting with the DBE to discuss future commencement and convocation activities in the new facilities is scheduled for Nov. 13. The 100% DD deliverable is scheduled for submission during the week of Nov. 16.
- Performing Arts Center / Administration & Parking Structure: The DBE is scheduled to submit the 100% DD deliverable during the week of Nov. 16.
Miramar College:
- Performing Arts Center & English/Gallery Building: The district is scheduled to complete its review of the 100% DD deliverable on Nov. 9.
- Early Education Center: A construction kickoff meeting with the DBE is scheduled for Nov. 9.
- Aviation Instructional Center: The civil engineer is expected to provide a survey drawing for the potential alternative site during the week of Nov. 11.
- Pool Deck Replacement and Replaster: Bids are due Nov. 13.
College of Continuing Education:
- ECC Ceramics Renovation: A landscape site walk is scheduled for Nov. 10.
- New Site for SDCCE: A stakeholder design meeting is scheduled for Nov. 10.
- CE Mesa Building Improvements: A design presentation to the Executive Presidents Committee (EPC) is scheduled for Nov. 10.
- West City Expansion: A pre-application meeting with DSA is scheduled for Nov. 12.
- ECC Welding: An equipment coordination meeting with stakeholders is scheduled for Nov. 13.
Other District Locations:
No items to report.
Key Items of Interest
Miramar
- Aviation Instructional Center: Design at the current location will be paused until California Environmental Quality Act (CEQA) comments are received at the end of November. In the interim, the DBE has been tasked with studying the Terminal Building at Montgomery Field Airport (MYF) in case the current site is deemed unviable.
Upcoming Needed Campus Action Items (Time Sensitive)
No items to report.