S-100 Mechanical Unit Replacement

Project Schedule

Programming Complete Design and DSA Approval Construction Completion (Est.) FFE and Move-In (Est.)
01-2026 05-29-2026 01-29-2027 N/A

Current Status/Phase: Design Phase

Project Insights

As of May 26, 2026, the DSA resubmittal was completed and the DSA review is due on May 29, 2026. If necessary, an over-the-counter review will be conducted in mid-June.

Upcoming Milestones:

Project Features

Project Map

Mesa S100 Map

7250 Mesa College Dr, San Diego, CA 92111

Project Schedule

Mesa s100 schedule

Project News & Information

Additional resources, articles, and links related to this project will appear here when available. For comprehensive information about Measure HH and all ongoing projects, please explore the Measure HH website.

Project Teams

General Contractor TBD
Architect N/A
Structural Engineer N/A
Civil Engineer N/A
Mech./ Elect. Engineer H + W Engineering
Executive Const. Manager Jonathan Cruz

 

Last updated: June 1, 2026